| Project Activities | Duration (Week) | Precedence |
|---|---|---|
| A | 2 | |
| B | 3 | A |
| C | 4 | A |
| D | 5 | B, C |
| E | 2 | D |
Draw activity-on-arrow diagram for the above scenario and find the critical path.
Explain incremental delivery approach with a neat diagram. What are its advantages and disadvantages?
What is cost estimation? Explain COCOMO II with respect to post architecture effort multipliers. Lists its advantages.
Attempt any Eight questions
[8x5=40]Explain how we can select the right person for the job.
What is a contract? Explain contract management process.
Explain modern project management practices. List out the importance of project management.
Explain any two methods that can be used to visualize progress of a project.
What are different classification of coordination dependencies that exists in an organization? Explain.
Explain the significance of Break Event Point and Return on Investment.
Explain different approaches that can be used to handle risk.
Briefly explain the techniques that can be used to enhance the software quality.
Write short notes on
a. Scrum
b. Resource schedule